IBPS Result & Government Jobs 2016

IBPS Bank PO, SO, Clerk

Daily Aptitude for LIC AAO and other bank exams : Time and Work questions

  • Practice set time and work questions (Level-1)
  1.  10 men can do a piece of work in 5 days, How many men are needed to complete a work in 25 days?
    a) 2 men          b) 4 men          c) 1 men          d) 5 men
    Answer
  2. A finish a work in 5 days, B finish the same work in 20 days, How long will they take to finish the same work together?
    a) 5 days         b)10 days         c) 3 days         d) 4 days
    Answer
  3. 20 men can prepare 40 toys in 24 days working 18 hours a day. then in how many days can 36 men prepare 48 toys working 16 hours a day?
    a) 16 days        b) 12 days       c) 21 days       d) 18 days
    Answer
  4. A finish a work in 4 days, B took 12 days to finish the same work and C took 20 days, in how many days working together, A, B and C will finish the work.
    a)60/23 days    b)55/23 days    c)40/23 days   d)50/23 days
    Answer
  5. if 3 men or 5 women can reap a field in 43 days, how long will 5 men and 6 women take to reap it.
    a) 15 days        b) 25 days       c) 18 days       d)12 days
    Answer
  6. A and B finish a job in 12 days, while A, B and C can finish it in 8 days, C alone will finish the job in;
    a) 16 days        b) 24 days       c) 14 days       d) 20 days
    Answer
  7. shivam can finish a work in 16 days at 5 hrs a day, Arun can finish it in 12 days at 4 hrs a day, find in how many ways, both can finish it in working 6 hrs a day.
    a) 4 days          b)6 days          c) 7 days         d) 5 days
    Answer
  8. A and B can together do a piece of work in 7 days, if A does twice as much work as B in a given time, find how long A alone would take to do the work.
    a) 21 days        b) 19/2 days       c) 10 days        d)21/2 days
    Answer
  9. A is twice as fast as B, and is therefore able to finish a work in 30 days less than B. Find the time in which they can do it working together.
    a)16 days         b) 20 days          c) 24 days        d) 21 days
    Answer
  10. A certain number of men can do a work in 45 days. if there were 4 men less it could be finished in 15 days more. How many men are there?
    a)16 men           b) 20 men          c) 12 men       d) 18 men
    Answer
Also Read:  Simplification Notes-Tricks & Question
Updated: June 28, 2016 — 3:19 am

Leave a Reply

Your email address will not be published. Required fields are marked *

IBPS Result & Government Jobs 2016 © 2016 Frontier Theme